I am writing to advise you that work on the above scheme has been programmed to start week commencing Monday 22-2-2010 and will take approximately four weeks to complete.

The scheme will include the construction of the following:

a)        Improvements to direction signs, together with the provision of new countdown markers and chevrons, at both the eastbound and westbound A31/B3000 junctions.

b)        Localised carriageway widening on the corner of the westbound A31/B3000  diverging lane.

c)        Extension of the two splitter islands on either side of the A31.

d)        Improvements to directions signs at the Wanborough Hill and Puttenham Hill junctions.

e)        Improvements to road markings and reflective road studs on the A31 and at the Wanborough Hill and Puttenham Hill junctions .

Due to the high speed and volume of traffic using the A31, it will be necessary to impose temporary lane 1 closures (both directions but not concurrently) to protect the workforce. These will operate off-peak Monday to Friday between 9.30am and 4.00pm (3.30pm on Friday).  The lane 1 closures will also operate over two weekends during the construction period, from Friday night (after the peak hour) to Sunday afternoon, to facilitate the extension of the two splitter islands.

Traffic management for the proposed signing work at the Wanborough Hill and Puttenham Hill junctions will be by portable three-way traffic signals, operating off-peak.

For safety reasons, it will necessary to suspend the two local bus stops for the duration of the works.

Our contractor will shortly be erecting advance warning signs and arranging a letter drop to properties affected by the scheme. However, any assistance you can provide in further publicising the scheme would be very much appreciated.

Information will also be available on our public website by following this link

If you have any queries or need any further information about the scheme, please do not hesitate to contact me.


Chris Baker
Engineer
Surrey Highways (West)

Tel: (020) 8541 7161
Mob: 07768 501415
Email: wah@surreycc.gov.uk

15:25, 28 Feb 2010 by Gill Haworth

Westwood Lane, will be closed on 5 March 2010 for Network Rail.

==============================
Section of Road to be closed:

Westwood Lane, 20m either side of the railway bridge.

Dates/times of closure:

The works are anticipated to take place:

09:30h to 15:30h Friday 5 March 2010.

Temporary Traffic Regulation Order & Diversion Route:



Diversion route is:  Flexford Road, Glaziers Lane, Guildford Road and Westwood Lane or this route in reverse order.

Other information:

Access will be maintained for emergency services and residents at all times.
==============================


Please do not hesitate to contact me if you have any queries or concerns.


Andrew Porter
Engineering Technician - Surrey Highways

Tel:  01483 519 585

15:40, 26 Feb 2010 by Gill Haworth

 
HIGH SHERIFF YOUTH AWARD 2010
 
We have won the High Sheriff Youth Awards for the second year running, which is apparently unheard of!
So we have been very lucky.
 
I have just received a cheque in the post from the High Sheriff for £1000 this morming, so that is excellent news for us all to get more equipment and facilities for the youth club. So shoppping lists at the ready boys and girls. Onwards and upwards. 
 
Well Done to all you good friends, supervisors and supports, thank you for making it such a stimulating youth club to belong to.
 
Maria


15:24, 11 Feb 2010 by Gill Haworth

Archive

Use the calendar or list of months to view entries made on those dates.

< Feb March 2010 Apr >
S M T W T F S
  1 2 3 4 5 6
7 8 9 10 11 12 13
14 15 16 17 18 19 20
21 22 23 24 25 26 27
28 29 30 31      

Notifications

You may request email notification for when this page is updated. Note: you must be registered with SurreyCommunity to receive notifications. If you haven't already registered, by clicking on this link you will be taken to the 'Register' page. Please follow the onscreen instructions.

RSS Feed

If you have a feed reader you can use this link to get updates.

RSS feed